Where paper permits break down
The principles of permit to work are well known: plan the work, identify hazards, isolate energy, test the atmosphere, brief the team, authorise, monitor and hand back. Our guide to permit to work systems covers them in detail. This article shows how SafetyPro puts those principles into daily practice.
On paper, the weak points are always the same. A permit is signed without a current gas test. Two permits overlap in the same area. A permit runs past its end time because nobody noticed. The toolbox talk happened, but nobody can prove it covered this job.
Twelve permit types with their own rules
SafetyPro includes 12 permit types: Hot Work, Confined Space Entry, Work at Height, Excavation, Lifting Operations, Electrical / LOTO, Demolition, Radiography, Chemical Handling, Pressure Testing, Night Work and General. They are grouped as hot, cold, weather / special and general permits.
Each type brings its own default hazards and controls, PPE, pre-work checklist and closure checklist. Hot Work, for example, comes with checks such as clearing combustible materials within 15 m and assigning a fire watch, and its closure checklist asks for the area to be monitored for 30 minutes after work stops. Every permit is limited to a maximum validity of 12 hours.
A clear chain of authorization
Every permit names three people from the active project team: the Permit Holder (PH), the Authorized Person (AP) and the Permit Control Manager (PCM). The permit then moves through a defined workflow:
- Draft: the permit is prepared.
- Submitted: the Permit Holder signs a declaration that the work party was briefed and the toolbox talk was completed.
- Issued: the Authorized Person authorizes the permit.
- Pending Approval: the Permit Control Manager reviews it.
- Approved: work is authorized.
- Handed Back: the Permit Holder returns the permit when work ends.
- Closed: the Authorized Person completes the closure inspection.
Permits can also be rejected, suspended, returned to active work, extended or cancelled. Only the people assigned to the permit, or users with full access, see the actions that apply to them. Every step is stored in the permit history with the person and the time.
Gas testing that the platform actually checks
Hot Work and Confined Space Entry permits cannot be submitted without a linked Gas Testing Certificate. SafetyPro does not just check that a certificate exists. It checks that the certificate:
- is Approved or Active, belongs to the same project and covers the same location as the permit;
- records the test equipment, a completed initial test and at least one atmospheric reading;
- has every reading marked Pass and inside the limits;
- has its latest reading taken within 30 minutes before the permit is issued.
The default acceptance limits are oxygen between 19.5% and 23.5%, LEL below 10%, H2S up to 10 ppm and CO up to 25 ppm. A site can make these limits stricter, but not looser. Authorized users can record hourly gas retests on the certificate, and a failed retest is kept as evidence.
O2 19.5-23.5 % | LEL < 10 % | H2S <= 10 ppm | CO <= 25 ppm
Isolation certificates and LOTO
Isolation is managed through certificates linked to the permit: Electrical Isolation, Mechanical Isolation, Gas Testing, Ground Disturbance and Ionizing Radiation. Excavation permits require a Ground Disturbance Certificate. Certificates follow their own workflow, from Draft and Submitted to Approved and Active, and can be suspended, reactivated or closed and reinstated. Each one can be printed.
For Electrical / LOTO work, the permit records each isolation point with its point ID, energy source, LOTO sequence and lock holder. The checklist confirms that locks and tags are applied at every isolation point and that zero energy was verified with a try-start test, and the closure checklist confirms that isolation points were restored.
Toolbox talks and the work party
A permit cannot be submitted without a linked toolbox talk. It must be a completed toolbox talk from the same project, and not one already linked to a different permit. The work party must match the declared number of workers, or be covered by a verified signed work party sheet, and every member must acknowledge the permit hazards and controls before submission. If a contractor Safety Passport is Suspended, the permit cannot be issued until the compliance gaps are resolved.
Automatic expiry, shift revalidation and gas monitoring
A scheduled server task runs every minute. Any permit that is Issued, Pending Approval, Approved, Suspended or Handed Back and has passed its end time is set to Expired, using the company time zone, and the reason is written into the permit history. Nobody has to remember to expire a permit.
The same task also watches gas monitoring. An Approved Hot Work or Confined Space Entry permit with no passing gas reading in the last hour is suspended, with the note that work must stop until it is revalidated.
At each shift change, permits can be revalidated: the incoming Permit Holder is recorded, safety checks are confirmed and remarks are added. Extensions are made by the Authorized Person with a reason, and the old and new end times are both kept. A permit whose validity has already ended cannot be extended.
A live view of active permits
The Active Permits view shows every live permit as a card with its type, location, validity and time remaining. Permits ending within 90 minutes are highlighted. Summary cards show active permits, permits pending approval, permits expiring today, toolbox talks this month, permits handed back and awaiting inspection, certificates pending, overdue permits not closed and permits closed this week.
SafetyPro also checks for conflicts. When two active permits share the same location and their times overlap, a warning banner appears. If one is Hot Work and the other is Confined Space Entry, the pair is flagged as a high risk combination.
PDF permits and mobile access
Each permit exports to a structured PDF: permit details, authorization roles, work party and individual worker signatures, contractor breakdown, linked toolbox talk, pre-work checklist, PPE, isolation certificates, simultaneous activities, hazard assessment, shift revalidations, the full approval journey and signatures. Your published report template can set the header and footer.
In the SafetyPro mobile app, permit users can browse the permit register, open permit details and take the workflow actions assigned to them, such as submit, issue, send for approval, approve, return to the Permit Holder, suspend and reactivate. Certificates, including new gas retest readings, worker signatures and toolbox talk links, are also available on the phone.
Rolling it out on your site
- Agree who acts as Permit Holder, Authorized Person and Permit Control Manager on each project, and make sure they are active project users.
- Review the default hazards and checklists for your most common permit types.
- Train gas testers to record readings on the certificate, including hourly retests.
- Make the linked toolbox talk part of every morning start.
- Use the Active Permits view in the daily coordination meeting to check expiring permits and conflicts.